Lakeview Parkway Widening and Resurfacing Project
Project Schedule
Construction will begin in May 2023 with completion in December 2023, and final tree planting in spring 2024.
Project Details
2000’ of resurfacing
3300’ of widening/resurfacing
1800’ of reconstructed bike path
400’ of new sidewalk
Replace streetlights, upgrade to LED
Replace traffic signals
Upgraded Sidewalk Curb Ramps
Additional through lane capacity
on Lakeview
New dedicated eastbound left turn lane
on eastbound Hawthorn at Lakeview
Additional left turn lane on northbound
Lakeview at Hawthorn
Sign Up to Receive Project Updates
What to Expect
- Traffic Staging – One through lane in each direction will remain open. One left turn lane will remain open on each leg of intersections.
- Driveway Access and Parking – Driveway access will be maintained through the project duration. This will be accomplished with temporary stone, working on driveways half at a time, and/or alternating work on properties with multiple driveways.
- Daily Work Hours – Potentially six days per week as project activity dictates. There may be a need for occasional overnight work as well.
- Dust Control – Dust control measures will be implemented and monitored.
- Construction Safety – This type of work requires heavy machinery. Please exercise caution near construction zone.
Project Team & Contacts
Village of Vernon Hills
Public Works & Engineering
847-367-3726
www.vernonhills.org/304/Public-Works-Engineering
Civiltech Engineering, Inc.
Mr. Brian J. Carroll, P.E.
Senior Resident Engineer